Reliability Committee Materials
May 2, 2006
Advises ISO-NE about the design and oversight of reliability standards for New England and the development of the annual Regional System Plan issued by ISO-NE.
| Date |
Document Title |
Document Type |
|
| Apr 07, 2006 |
Steady State System Impact Study Report |
 |
PDF (218k) |
|
| Apr 07, 2006 |
Transient Stability Analysis - Transmission Facilities Proposed Plan Analysis |
 |
DOC (1.8Mb) |
|
| Apr 06, 2006 |
(Transient Stability Analyses) prepared by Oswaldo Ortega, Northeast Utilities Transmission Planning |
 |
PDF (1.0Mb) |
|
| Aug 30, 2005 |
Middletown Area - Proposed Plan Application Analysis (Thermal and Voltage Study) prepared by Oswaldo Ortega, Northeast Utilities Transmission Planning |
 |
PDF (1010k) |
|
| May 01, 2006 |
Steady State and Short Circuit Analyses for I.3.9 Approval - Report prepared by E*PRO Engineering & Environmental Consulting, LLC |
 |
PDF (948k) |
|
| May 01, 2006 |
Report prepared by E*PRO Engineering & Environmental Consulting, LLC |
 |
PDF (324k) |
|
| May 02, 2006 |
For May 2, 2006 meeting |
 |
DOC (102k) |
|
| May 02, 2006 |
Regarding BHE-06-T01 Hancock County Reliability project |
 |
DOC (32.5k) |
|
| May 02, 2006 |
For May 2, 2006 meeting - Revision 1 |
 |
DOC (101k) |
|
| May 02, 2006 |
Regarding BHE-06-T02 Downeast Reliability project |
 |
DOC (32.5k) |
|
| Apr 04, 2006 |
CL&P Service Area - Proposed Plan Application Analysis (Steady State Analysis) prepared by Kiet A. Nguyen, Northeast Utilities Transmission Planning |
 |
PDF (409k) |
|
| Apr 01, 2006 |
Draft report prepared by Chuanjiang Zhu, National Grid |
 |
DOC (35k) |
|
| Feb 24, 2006 |
Proposed Plan Application Analysis prepared by Steven Masse, NSTAR System Planning |
 |
PDF (401k) |
|
| Mar 01, 2006 |
Report prepared by Chuanjiang Zhu, National Grid |
 |
DOC (219k) |
|
| Mar 01, 2006 |
Report prepared by Chuanjiang Zhu, National Grid |
 |
DOC (138k) |
|
| Apr 06, 2006 |
Application from Bangor Hydro Electric Co. for new transmission from Boggy Brook, Ellsworth, Maine to Trenton Sub - New facility |
 |
DOC (333k) |
|
| Apr 14, 2006 |
Application from Bangor Hydro Electric Co. for new transmission from Tap Line 61 from Boggy Brook in Hancock to Harrington substation, Harrington, Maine |
 |
DOC (336k) |
|