Reliability Committee Materials
Aug 18 & 20, 2008
Advises ISO-NE about the design and oversight of reliability standards for New England and the development of the annual Regional System Plan issued by ISO-NE.  

Date Document Title Document Type
Aug 14, 2008
08/18 Agenda Revision 2, 08/20 Agenda Revision 1, Motions for Consideration Revision 1
ZIP (82.4k)
Aug 05, 2008
Studies to support the PPAs for the New England East West Solution (NEEWS) projects.
ZIP (4.6Mb)
Aug 12, 2008
80 kA Guidelines, OP 18 Appendix A and Dartmouth Power QRR
ZIP (180k)
Aug 13, 2008
For Amherst College and Gorge Substation plans; and for 80 kA guidelines and PP10 FCM changes.
ZIP (709k)
Aug 14, 2008
Materials for Holy Name Wind, NU Neews Presentation, OP 7, Towantic Energy and Operations Reliability Review.
ZIP (2.3Mb)
Aug 14, 2008
NGRID's presentation and task force letter.
ZIP (1.7Mb)
Aug 18, 2008
Presentation.
ZIP (343k)
Aug 05, 2008
NU's PPAs for NEEWS, NU-08-T11 thru NU-08-T39 and NU-08-T49 thru NU-08-T67.
ZIP (1.5Mb)
Aug 05, 2008
NEP's PPAs for NEEWS, NEP-08-T44 thru NEP-08-T57, NEP-08-T59 and NEP-08-T60.
ZIP (2.1Mb)
Aug 06, 2008
Studies supporting NEP's HVDC hybrid configuration for the Phase II tie and changes to interconnection of VELCO's Gorge Substation in VT.
ZIP (1012k)
Aug 06, 2008
Studies supporting NSTAR's proposed installation of a shunt reactor at Mystic Substation and Towantic's proposed generation in CT.
ZIP (4.3Mb)
Aug 13, 2008
For Augusta, Groveton, Phase II HVDC Hybrid, Mystic (MA) reactors, Neighborhood Energy, Newcastle, Orono Hydro, SE MA Switches, and Towantic.
ZIP (1.7Mb)
Aug 08, 2008 ZIP (1.6Mb)
Aug 12, 2008
For NEP-08-TCA-03, NSTAR-08-TCA-01 and CMP-08-TCA-06
ZIP (2.6Mb)
Aug 12, 2008
PPA materials for Amherst College, Cos Cob, Glenbrook SPS, Gorge Substation, Groveton and Mystic 13K in CT; and recommendations for Mystic Reactors in MA and Phase II HVDC Hybrid
ZIP (3.0Mb)
  Copyright ©2009 ISO New England Inc.