Appendix H - Operations During Cold Weather Conditions

There are three distinct levels of weather situations that may precede ISO New England calling a Cold Weather Event:

  • Cold Weather Conditions means any calendar day when that day's Effective Temperatures are forecast to be equal to or less than zero degrees Fahrenheit for any single on-peak hour and that day's total Effective Heating Degree Days are forecast to be greater than or equal to 65.
  • Cold Weather Watch means Days when Cold Weather Conditions are forecast to exist and the 7-Day Capacity Margin Forecast indicates a capacity margin greater than or equal to 1,000 MW.
  • Cold Weather Warning means Days when Cold Weather Conditions are forecast to exist and the 7-Day Capacity Margin Forecast indicates a capacity margin less than 1,000 MW.  In addition, a Cold Weather Warning will be used for all future days within the 7-Day Capacity Margin Forecast when a capacity margin of less than or equal to 0 MW exists for days not yet declared as a Cold Weather Event.
  • Cold Weather Event means Days when Cold Weather Conditions are forecast to exist and the 7-Day Capacity Margin Forecast indicates a capacity margin less than or equal to 0 MW for an Operating Day.  Cold Weather Events are declared by 1100 hrs two days prior to the Operating Day. A Cold Weather Warning will be used for all future days within the 7-Day Capacity Margin Forecast when a capacity margin of less than or equal to 0 MW exists, until such time that the ISO declares a Cold Weather Event.

The September 1 filing allows for the recovery of Extraordinary Fuel Expenses during Cold Weather Events.  However, to recover costs in excess of $1000/MWh, Participants must:

  1. Once a Cold Weather Event Day is declared, notify ISO-NE, via email to custserv@iso-ne.com, prior to the close of the applicable Day-Ahead Energy Market that a claim for "Extraordinary Fuel Expense"  is expected; 
  2. Submit Supply Offers into the Day-Ahead and Real-Time markets, subject to all market monitoring and mitigation provisions, including incremental energy offers equal to the maximum level accepted in the Market User Interface.
  3. Within 15 calendar days of the operating day for which a Cold Weather Event day was declared, submit via email to custserv@iso-ne.com documentation specifying the Extraordinary Fuel Expenses requested and the supporting calculations of the requested amounts; and
  4. Within 15 calendar days of receiving payment for Extraordinary Fule Expenses the Participant must filing with the Federal Energy Regulatory Commission (FERC) pursuant to section 205 of the Federal Power Act (FPA).  In addition, de-listed resources may seek compensation for "Extraordinary Fuel Expenses" even if fuel supply contracts were not submitted in advance of a Cold Weather Event.