Current Status |
|||||
| Report Name | Change Summary |
Effective Date |
Description |
Template |
Sample |
| sd_monthlyepoh | Modified. New column in Resource section entitled "Cumulative EPOH Exemption". This new column will be reported for both the initial settlement effective June 1st 2011 and any resettlements prior to June 1st 2011. | 06.01.2011 | XLTX | CSV | |
SD_MONTHLYEPOH – Monthly Equivalent Planned Outage Hours Settlement Detail Report – Rev 1SD_MONTHLYEPOH_<customer id>_<settlement date>_<version>.CSV |
|
REPORT COLUMN |
DESCRIPTION |
Asset |
|
Trading Date |
Specific day for which the information is reported. |
Trading Interval |
Specific hour for which the information is reported. Numeric from 1 – 24 (For daylight-saving crossover days: the long day extra hour = 02X, the short day removes hour 02). |
Asset ID |
Numerical identifier for the generating asset. |
Asset Name |
Name of the generating asset. |
Planned Outage Reduction MW |
The MW value of the outage for the generating asset submitted with the outage request. Only Planned Outages where the customer opted to have the outage MW considered exempt from Availability Penalties are included. |
Seasonal Claimed Capability |
The Summer (SCC-S) or Winter (SCC-W) Claimed Capability of the generating asset in MW quantity. |
Resource |
|
Trading Date |
Specific day for which the information is reported. |
Trading Interval |
Specific hour for which the information is reported. Numeric from 1 – 24 (For daylight-saving crossover days: the long day extra hour = 02X, the short day removes hour 02). |
Resource ID |
Numerical identifier for the Resource. |
Resource Name |
Name of the Resource. |
Resource Type |
The FCM Resource Type. Included types are: Generator and Import. |
Capacity Supply Obligation |
The MW value of the Resource's obligation to provide capacity acquired through the Forward Capacity Market. |
Resource Total SCC |
The sum of Seasonal Claimed Capability for generating assets associated to the Resource. |
Resource Planned Outage Reduction MW |
The sum of the lesser of the Planned Outage Reduction MW or the Seasonal Claimed Capability for generating assets associated to the Resource. |
Resource Planned Outage Limit MW |
The greater of zero, or the Resource Total SCC minus the Resource Planned Outage Reduction MW. |
Preliminary Resource Eligible Exempt MW |
The greater of zero, or the Capacity Supply Obligation minus the Resource Planned Outage Limit MW. |
Resource Eligible Exempt MW |
If the Remaining Available CP Allotment Hours are zero, then zero, otherwise the product of the lesser of the Resource Planned Outage Reduction MW or the Preliminary Resource Eligible Exempt MW multiplied by the quotient of the EPOH Exemption divided by the Initial EPOH Exemption. |
Available CP Allotment Hours |
The outage allotment hours available to the Resource as of the beginning of the Capacity Commitment Period. This value will be positive or zero. |
Remaining Available CP Allotment Hours |
The outage allotment hours available to the Resource as of the Trading Date and Interval. This value reflects all EPOH Exemption usage since the beginning of the Capacity Commitment Period and will be positive or zero. |
Initial EPOH Exemption |
The quotient of the lesser of the Resource Planned Outage Reduction MW or the Preliminary Resource Eligible Exempt MW divided by the Capacity Supply Obligation. |
EPOH Exemption |
The lesser of the Initial EPOH Exemption or the Remaining Available CP Allotment Hours. |
Cumulative EPOH Exemption |
The outage allotment hours used by the Resource as of the beginning of the Trading Date and Interval. This value reflects all EPOH Exemption usage since the beginning of the Capacity Commitment Period and will be positive or zero. |
Archived Status |
||
Report Name |
Change Summary |
Effective Date |
sd_monthlyepoh |
New. |
06.01.2010 |