sp_fcaresult |
Modified.The definitions of Payment Rate for Capacity Zone (Tab 4) and External Interface (Tab 5) have been changed, effective with the FCA for Capacity Commitment Period 2016-2017. | 02.08.2013 | XLTX | CSV | |
View Archived Status at the foot of this page |
|||||
SP_FCARESULT – Forward Capacity Auction Result Report – Rev 4SP_FCARESULT_<customer id>_<settlement date>_<version>.CSV |
||
|
REPORT COLUMN |
DESCRIPTION |
|
|
Tab 1 (Resource Total) |
||
|
Resource ID |
Numerical identifier for the Resource. |
|
|
Resource Name |
Name of the Resource. |
|
|
Resource Type |
The FCM Resource type. Appropriate values are: Generator, Demand and Import. |
|
|
Resource Subtype |
The FCM Resource subtype, if applicable. Appropriate values are:
|
|
|
Modeled Capacity Zone ID |
The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Modeled Capacity Zone Name |
The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Final Capacity Zone ID |
The numerical identifier of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction. |
|
|
Final Capacity Zone Name |
The name of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction. |
|
|
External Interface Name |
The name of the External Interface. |
|
|
Commitment Period Month |
The month in the Capacity Commitment Period. |
|
|
Qualified Capacity |
The seasonal qualified MW value of the Resource’s capacity. |
|
|
Permanent De-listed |
The MW value of permanent de-list bids cleared for the Resource in the Forward Capacity Auction. |
|
|
Total De-listed |
The total MW value for all de-list bid types cleared for the Resource in the Forward Capacity Auction. |
|
|
Capacity Supply Obligation |
The MW value of the Resource’s obligation to provide capacity acquired through the Forward Capacity Auction. |
|
|
Self-Supply Obligation |
The MW value of the Resource’s total Self-Supply Capacity Obligation MW. |
|
|
Estimated FCA Payment |
The sum of payments for all Capacity Supply Obligation types. |
|
|
FCA Financial Assurance MW |
The total MW value for which the New Capacity Resource has acquired an obligation and is subject to financial assurance. The customer’s financial assurance requirement will be the maximum MW value in the 12 month period reflected in this column for each New Capacity Resource. Effective with the third Forward Capacity Auction (Capacity Commitment Period 2012-2013), this column is no longer used and will be reported as NULL. |
|
|
Tab 2 (Resource Details) |
||
|
Resource ID |
Numerical identifier for the Resource. |
|
|
Resource Name |
Name of the Resource. |
|
|
Resource Type |
The FCM Resource type. Appropriate values are: Generator, Demand and Import. |
|
|
Resource Subtype |
The FCM Resource subtype, if applicable. Appropriate values are:
|
|
|
Modeled Capacity Zone ID |
The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Modeled Capacity Zone Name |
The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Final Capacity Zone ID |
The numerical identifier of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction. |
|
|
Final Capacity Zone Name |
The name of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction. |
|
|
External Interface Name |
The name of the External Interface. |
|
|
Commitment Period Month |
The month in the Capacity Commitment Period. |
|
|
Qualified Capacity |
The seasonal qualified MW value of the Resource’s capacity. |
|
|
Capacity Supply Obligation |
The MW value of the Resource’s obligation to provide capacity acquired through the Forward Capacity Auction. |
|
|
Obligation Type |
The type of capacity supply obligation. Valid types are:
|
|
|
Payment Rate |
FCA Payment Rate in $/kW-Month for the Capacity Supply Obligation associated with Resource Type, Location (Capacity Zone or External Interface) and Obligation Type. |
|
|
Estimated FCA Payment |
The product of the Capacity Supply Obligation and the payment rate. |
|
|
Special Provision |
An indicator noting any special considerations regarding reported auction results. Valid values are:
(Note: Effective with the fourth Forward Capacity Auction, if the Capacity Clearing Price Collar is reached and a resource’s subsequent MW proration request is denied, the resource will be paid the Capacity Clearing Price) |
|
|
Tab 3 (Resource De-list Details) |
||
|
Resource ID |
Numerical identifier for the Resource. |
|
|
Resource Name |
Name of the Resource. |
|
|
Resource Type |
The FCM Resource Type. Appropriate values are: Generator, Demand and Import. |
|
|
Resource Subtype |
The FCM Resource Type. Appropriate values are:
|
|
|
Modeled Capacity Zone ID |
The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Modeled Capacity Zone Name |
The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Final Capacity Zone ID |
The numerical identifier of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction. |
|
|
Final Capacity Zone Name |
The name of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction. |
|
|
External Interface Name |
The name of the External Interface. |
|
|
De-list Type |
The type of de-list bid cleared in the Forward Capacity Auction. Valid types are:
|
|
|
De-list Bid |
The MW value of the de-list bid. |
|
|
De-list Bid Price |
The price of the de-list bid. |
|
|
Accepted/Rejected |
Identify whether or not the de-list bid was accepted. Valid types are: Accepted, Rejected |
|
|
De-listed Capacity |
The cleared de-listed MW. |
|
|
Tab 4 (Capacity Zone) |
||
|
Modeled Capacity Zone ID |
The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Modeled Capacity Zone Name |
The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Modeled Capacity Zone Type |
The type of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. Valid types are:
|
|
|
Local Sourcing Requirement |
The minimum amount of capacity that must be acquired within an import-constrained Capacity Zone. |
|
|
Maximum Capacity Limit |
The maximum amount of capacity that can be procured in an export-constrained Capacity Zone. |
|
|
Capacity Supply Obligation |
The MW value of capacity acquired in the Capacity Zone through the Forward Capacity Auction including Real-Time Emergency Generation capacity capped by Real-Time Emergency Generation capacity limit. |
|
|
RTEG Capacity Supply Obligation |
The MW value of capacity from Real-Time Emergency Generation. |
|
|
Self-Supply Obligation |
The MW value of Self-Supply Capacity. |
|
|
Administrative Pricing |
An indicator noting whether the Capacity Clearing Price collar provisions were administered in the FCA. Appropriate values are:
|
|
|
Capacity Clearing Price |
The clearing price for the Capacity Zone. |
|
|
Payment Rate |
The rate paid to some or all Capacity Resources in the Capacity Zone (other than RTEG Capacity Resources) as a conclusion of FCA, which may be different than calculated Capacity Clearing Price due to one of the following conditions (specified by Administrative Pricing indicator): |
|
|
RTEG Payment Rate |
The Capacity Clearing Price adjusted for excess RT Emergency Generation. |
|
|
Tab 5 (External Interface) |
||
|
External Interface Name |
The name of the External Interface. |
|
|
Modeled Capacity Zone ID |
The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
Modeled Capacity Zone Name |
The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. |
|
|
External Control Area |
The name of the External Control Area. |
|
|
Capacity Transfer Limit |
The transfer limit of the interface. |
|
|
Capacity Supply Obligation |
The MW value of import capacity acquired over the External Interface through the Forward Capacity Auction. |
|
|
Grandfathered Import Capacity Supply Obligation |
The MW value of import capacity acquired over the External Interface through the Forward Capacity Auction from Import Capacity Resources granted priority access to the interface. |
|
|
Self-Supply Obligation |
The MW value of Self-Supply Capacity cleared at the interface in the Forward Capacity Auction. |
|
|
Administrative Pricing |
An indicator noting whether the Capacity Clearing Price collar provisions were administered in the FCA. Appropriate values are:
|
|
|
Capacity Clearing Price |
The external interface Clearing Price. |
|
|
Payment Rate |
The rate paid to some or all Capacity Resources in the Capacity Zone (other than RTEG Capacity Resources) as a conclusion of FCA, which may be different than calculated Capacity Clearing Price due to one of the following conditions (specified by Administrative Pricing indicator): |
|
|
Tab 6 (Control Area) |
||
|
Commitment Period |
The one-year period from June 1 through May 31. |
|
|
Installed Capacity Requirement |
The level of capacity required to meet the reliability requirements defined for the New England Control Area. |
|
|
HQICC |
The total MW value of the Hydro Quebec Interconnection Capability Credits. |
|
|
Net Installed Capacity Requirement |
The Installed Capacity Requirement minus the HQICC. |
|
|
Capacity Supply Obligation |
The MW value of capacity acquired in the Control Area through the Forward Capacity Auction including Real-Time Emergency Generation capacity capped by Real-Time Emergency Generation capacity limit. |
|
|
RTEG Capacity Supply Obligation |
The total MW value of Real Time Emergency Generation capacity. |
|
|
RTEG Utilization Ratio |
The ratio used to adjust the payment rate for Real Time Emergency Generation. |
|
|
Self-Supply Obligation |
The total Self-Supply Capacity Obligation MW for the control area. |
|
|
Import Capacity Supply Obligation |
The total Import Capacity Supply Obligation MW for the control area. |
|
|
Archived Status |
||
|
Report Name |
Change Summary |
Effective Date |
| sp_fcaresult | Modified. In the "Resource Total" section, the "FCA Financial Assurance MW [obsolete]" column will replace the "FCA Financial Assurance MW" column effective 12/01/2010. Starting with the 2012 commitment period and going forward, the modified column will appear on the report. | 12.01.2010 |
|
sp_fcaresult |
Existing. Effective with the third Forward Capacity Auction (Capacity Commitment Period 2012-2013), the "FCA Financial Assurance MW" column will no longer be used and will be reported as NULL. This report will be released a few days after the FCM clears the first week of October. |
Not available |
|
sp_fcaresult |
Modified. Resource Total section, clarified definition of "Qualified Capacity" as "seasonal" and renamed "FCA Payment" column to "Estimated FCA Payment". Resource Details section, clarified definition of "Qualified Capacity" as "seasonal" and detailed "Obligation Type" to be "Composite Offer Winter Contrib-Existing Cap Offer" or "Composite Offer Winter Contrib-New Cap Offer" as opposed to solely "Composite Offer Winter Contrib-Contribution", detailed "Self-Supply" to be "Self Supply-Existing Cap Offer" or "Self Supply-New Cap Offer", renamed "FCA Payment" column to "Estimated FCA Payment", and added column "Special Provision". The first version of this revised report is expected to be released early August 2010 effective with reporting of data for Capacity Commitment Period 2013-2014. |
08.01.2010 |