sp_fcaresult

Modified.The definitions of Payment Rate for Capacity Zone (Tab 4) and External Interface (Tab 5) have been changed, effective with the FCA for Capacity Commitment Period 2016-2017. 02.08.2013 PDF XLTX CSV

View Archived Status at the foot of this page

 

SP_FCARESULT – Forward Capacity Auction Result Report – Rev 4

SP_FCARESULT_<customer id>_<settlement date>_<version>.CSV
Date: mm/dd/yyyy and Version: mm/dd/yyyy hh:mm:ss GMT
Availability: Annually after the Forward Capacity Auction

REPORT COLUMN

DESCRIPTION

Tab 1 (Resource Total)

Resource ID

Numerical identifier for the Resource.

Resource Name

Name of the Resource.

Resource Type

The FCM Resource type. Appropriate values are: Generator, Demand and Import.

Resource Subtype

The FCM Resource subtype, if applicable. Appropriate values are:

  • Generator: Intermittent
  • Demand: RT Emergency Generation
  • Import: Grandfathered

Modeled Capacity Zone ID

The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Modeled Capacity Zone Name

The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Final Capacity Zone ID

The numerical identifier of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction.

Final Capacity Zone Name

The name of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction.

External Interface Name

The name of the External Interface.

Commitment Period Month

The month in the Capacity Commitment Period.

Qualified Capacity

The seasonal qualified MW value of the Resource’s capacity.

Permanent De-listed

The MW value of permanent de-list bids cleared for the Resource in the Forward Capacity Auction.

Total De-listed

The total MW value for all de-list bid types cleared for the Resource in the Forward Capacity Auction.

Capacity Supply Obligation

The MW value of the Resource’s obligation to provide capacity acquired through the Forward Capacity Auction.

Self-Supply Obligation

The MW value of the Resource’s total Self-Supply Capacity Obligation MW.

Estimated FCA Payment

The sum of payments for all Capacity Supply Obligation types.

FCA Financial Assurance MW
[Obsolete]

The total MW value for which the New Capacity Resource has acquired an obligation and is subject to financial assurance. The customer’s financial assurance requirement will be the maximum MW value in the 12 month period reflected in this column for each New Capacity Resource.  Effective with the third Forward Capacity Auction (Capacity Commitment Period 2012-2013), this column is no longer used and will be reported as NULL.

Tab 2 (Resource Details)

Resource ID

Numerical identifier for the Resource.

Resource Name

Name of the Resource.

Resource Type

The FCM Resource type. Appropriate values are: Generator, Demand and Import.

Resource Subtype

The FCM Resource subtype, if applicable. Appropriate values are:

  • Generator: Intermittent
  • Demand: RT Emergency Generation
  • Import: Grandfathered

Modeled Capacity Zone ID

The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Modeled Capacity Zone Name

The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Final Capacity Zone ID

The numerical identifier of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction.

Final Capacity Zone Name

The name of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction.

External Interface Name

The name of the External Interface.

Commitment Period Month

The month in the Capacity Commitment Period.

Qualified Capacity

The  seasonal qualified MW value of the Resource’s capacity.

Capacity Supply Obligation

The MW value of the Resource’s obligation to provide capacity acquired through the Forward Capacity Auction.

Obligation Type

The type of capacity supply obligation. Valid types are:

  • Retained for Reliability
  • Existing Capacity Offer
  • New Capacity Offer
  • Multiyear Rate Existing Capacity Offer
  • Composite Offer Winter Contrib-Existing Cap Offer
  • Composite Offer Winter Contrib-New Cap Offer
  • Self Supply-Existing Cap Offer
  • Self Supply-New Cap Offer

Payment Rate

FCA Payment Rate in $/kW-Month for the Capacity Supply Obligation associated with Resource Type, Location (Capacity Zone or External Interface) and Obligation Type.

Estimated FCA Payment

The product of the Capacity Supply Obligation and the payment rate.

Special Provision

An indicator noting any special considerations regarding reported auction results. Valid values are:

  • Rejected for MW Proration 

(Note:  Effective with the fourth Forward Capacity Auction, if the Capacity Clearing Price Collar is reached and a resource’s subsequent MW proration request is denied, the resource will be paid the Capacity Clearing Price)

Tab 3 (Resource De-list Details)

Resource ID

Numerical identifier for the Resource.

Resource Name

Name of the Resource.

Resource Type

The FCM Resource Type. Appropriate values are: Generator, Demand and Import.

Resource Subtype

The FCM Resource Type. Appropriate values are:

  • Generator: Intermittent
  • Demand: RT Emergency Generation
  • Import: Grandfathered

Modeled Capacity Zone ID

The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Modeled Capacity Zone Name

The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Final Capacity Zone ID

The numerical identifier of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction.

Final Capacity Zone Name

The name of the Capacity Zone in which an offer or bid for the Resource cleared in the Forward Capacity Auction.

External Interface Name

The name of the External Interface.

De-list Type

The type of de-list bid cleared in the Forward Capacity Auction. Valid types are:

  • Permanent
  • Static
  • Dynamic
  • Administrative
  • Export

De-list Bid

The MW value of the de-list bid.

De-list Bid Price

The price of the de-list bid.

Accepted/Rejected

Identify whether or not the de-list bid was accepted. Valid types are: Accepted, Rejected

De-listed Capacity

The cleared de-listed MW.

Tab 4 (Capacity Zone)

Modeled Capacity Zone ID

The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Modeled Capacity Zone Name

The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Modeled Capacity Zone Type

The type of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market. Valid types are:

  • Import
  • Export
  • Rest of Pool

Local Sourcing Requirement

The minimum amount of capacity that must be acquired within an import-constrained Capacity Zone.

Maximum Capacity Limit

The maximum amount of capacity that can be procured in an export-constrained Capacity Zone.

Capacity Supply Obligation

The MW value of capacity acquired in the Capacity Zone through the Forward Capacity Auction including Real-Time Emergency Generation capacity capped by Real-Time Emergency Generation capacity limit.

RTEG Capacity Supply Obligation

The MW value of capacity from Real-Time Emergency Generation.

Self-Supply Obligation

The MW value of Self-Supply Capacity.

Administrative Pricing

An indicator noting whether the Capacity Clearing Price collar provisions were administered in the FCA. Appropriate values are:

  • Not Applicable
  • CCP Collar – Floor
  • CCP Collar – Ceiling
  • Alternative Price Rule
  • Insufficient Competition
  • Inadequate Supply

Capacity Clearing Price

The clearing price for the Capacity Zone.

Payment Rate

The rate paid to some or all Capacity Resources in the Capacity Zone (other than RTEG Capacity Resources) as a conclusion of FCA, which may be different than calculated Capacity Clearing Price due to one of the following conditions (specified by Administrative Pricing indicator):
CCP Collar – Floor:
Rate adjusted for excess capacity and paid to both new and existing capacity resources
Inadequate Supply
Rate established according to pricing rule for Inadequate Supply and paid only to existing capacity resources while new capacity resources are paid full Capacity Clearing Price.
Insufficient Competition
Rate established according to pricing rule for Inadequate Supply and paid only to existing capacity resources while new capacity resources are paid full Capacity Clearing Price.
Alternative Price Rule
Rate established according to pricing rule for APR and paid to both new and existing capacity resources.

RTEG Payment Rate

The Capacity Clearing Price adjusted for excess RT Emergency Generation.

Tab 5 (External Interface)

External Interface Name

The name of the External Interface.

Modeled Capacity Zone ID

The numerical identifier of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

Modeled Capacity Zone Name

The name of the Capacity Zone to which the Resource is interconnected for the Forward Capacity Market.

External Control Area

The name of the External Control Area.

Capacity Transfer Limit

The transfer limit of the interface.

Capacity Supply Obligation

The MW value of import capacity acquired over the External Interface through the Forward Capacity Auction.

Grandfathered Import Capacity Supply Obligation

The MW value of import capacity acquired over the External Interface through the Forward Capacity Auction from Import Capacity Resources granted priority access to the interface. 

Self-Supply Obligation

The MW value of Self-Supply Capacity cleared at the interface in the Forward Capacity Auction.

Administrative Pricing

An indicator noting whether the Capacity Clearing Price collar provisions were administered in the FCA. Appropriate values are:

  • Not Applicable
  • CCP Collar – Floor
  • CCP Collar – Ceiling
  • Alternative Price Rule
  • Insufficient Competition
  • Inadequate Supply

Capacity Clearing Price

The external interface Clearing Price.

Payment Rate

The rate paid to some or all Capacity Resources in the Capacity Zone (other than RTEG Capacity Resources) as a conclusion of FCA, which may be different than calculated Capacity Clearing Price due to one of the following conditions (specified by Administrative Pricing indicator):
CCP Collar – Floor:
Rate adjusted for excess capacity and paid to both new and existing capacity resources
Inadequate Supply
Rate established according to pricing rule for Inadequate Supply and paid only to existing capacity resources while new capacity resources are paid full Capacity Clearing Price.
Insufficient Competition
Rate established according to pricing rule for Inadequate Supply and paid only to existing capacity resources while new capacity resources are paid full Capacity Clearing Price.
Alternative Price Rule
Rate established according to pricing rule for APR and paid to both new and existing capacity resources.

Tab 6 (Control Area)

Commitment Period

The one-year period from June 1 through May 31.

Installed Capacity Requirement

The level of capacity required to meet the reliability requirements defined for the New England Control Area.

HQICC

The total MW value of the Hydro Quebec Interconnection Capability Credits.

Net Installed Capacity Requirement

The Installed Capacity Requirement minus the HQICC.

Capacity Supply Obligation

The MW value of capacity acquired in the Control Area through the Forward Capacity Auction including Real-Time Emergency Generation capacity capped by Real-Time Emergency Generation capacity limit.

RTEG Capacity Supply Obligation

The total MW value of Real Time Emergency Generation capacity.

RTEG Utilization Ratio

The ratio used to adjust the payment rate for Real Time Emergency Generation.

Self-Supply Obligation

The total Self-Supply Capacity Obligation MW for the control area.

Import Capacity Supply Obligation

The total Import Capacity Supply Obligation MW for the control area.

 

Archived Status

Report Name

Change Summary

Effective Date

sp_fcaresult Modified.  In the "Resource Total" section, the "FCA Financial Assurance MW [obsolete]" column will replace the "FCA Financial Assurance MW" column effective 12/01/2010. Starting with the 2012 commitment period and going forward, the modified column will appear on the report. 12.01.2010

sp_fcaresult

Existing. Effective with the third Forward Capacity Auction (Capacity Commitment Period 2012-2013), the "FCA Financial Assurance MW" column will no longer be used and will be reported as NULL. This report will be released a few days after the FCM clears the first week of October.

Not available

sp_fcaresult

Modified. Resource Total section, clarified definition of "Qualified Capacity" as "seasonal" and renamed "FCA Payment" column to "Estimated FCA Payment".  Resource Details section, clarified definition of "Qualified Capacity" as "seasonal" and detailed "Obligation Type" to be "Composite Offer Winter Contrib-Existing Cap Offer" or "Composite Offer Winter Contrib-New Cap Offer" as opposed to solely "Composite Offer Winter Contrib-Contribution", detailed "Self-Supply" to be "Self Supply-Existing Cap Offer" or "Self Supply-New Cap Offer", renamed "FCA Payment" column to "Estimated FCA Payment", and added column "Special Provision".  The first version of this revised report is expected to be released early August 2010 effective with reporting of data for Capacity Commitment Period 2013-2014.