ww_ncpcsum
Net Commitment Period Compensation Summary

Current Status

Report Name

Change Summary

Effective Date

Description

Template

Sample

ww_ncpcsum Modified. In the LSCPR NCPC section, column heading changed from "DA NCPC Load Obligation" to "DA NCPC - Load Obligation Allocator" with a modified description; modified "DA LSCPR NCPC Rate" description. 01.23.2014 PDF XLTX CSV
Access Net Commitment Period Compensation Credits Summary Data

 

WW_NCPCSUM - Net Commitment Period Compensation Summary Report – Rev 5

WW_NCPCSUM_ISO_settlement date_version.CSV
Date: mm/dd/yyyy and Version: mm/dd/yyyy hh:mm: ss GMT

Availability: Monthly

Size:  One record per day in specified month.

Description:
This report is issued monthly and provides daily or hourly detailed data supporting the variety of NCPC charge allocation mechanisms and the associated charge rate for each MWh of a particular allocation.

This report contains six report sections:

  1. Asset & Ext. Node Economic NCPC
    • This section prints a detail line with summarized Economic Day-Ahead (assets only) and Economic Real-Time NCPC settlement information for each day of the specified month.
  2. LSCPR NCPC
    • This section prints a detail line with summarized LSCPR Day-Ahead and LSCPR Real Time NCPC settlement information for each day of the specified month by reliability region.
  3. External Node Economic NCPC
    • This section prints a detail line with summarized Economic Day-Ahead settlement information at the External Nodes for each hour of the specified month.
  4. VAR NCPC (excluding high voltage VAR)
    • This section prints a detail line with summarized Day Ahead and Real Time VAR settlement information (not related to high voltage conditions) for each hour of the month prior to the specified month or the specified month in the case of the Data Reconciliation and Meter Data Error RBA Process versions.
  5. High Voltage VAR NCPC
    • This section prints a detail line with summarized Day Ahead and Real Time VAR settlement information related to high voltage conditions (including any High Voltage VAR Cost Reallocation charges) by region for each hour of the month prior to the specified month or the specified month in the case of the Data Reconciliation and Meter Data Error RBA Process versions.
  6. Generator Performance Audit NCPC
    • This section prints a detail line with summarized Real Time Generator Performance Audit NCPC settlement information for each day of the specified month.

This report is generated when all NCPC settlements for the specified month are completed and ready to be billed.

This report is regenerated when 90-day resettlements are completed for the month.

Detail:
The first position on every record is occupied by the character ‘C’, ‘H’, ‘D’, or ‘T’ which describes what is contained on
that record (row.)
C= Comment – provides description such as report name and vintage.
H= Heading – denotes column headings.
D= Data – denotes data contained on the record.
T= Terminate – denotes the end of the file. The total number of ‘D’ lines contained in the file is also noted on this record.

REPORT COLUMN

DESCRIPTION

Asset & Ext. Node Economic NCPC tab

1

Operating Day

 

Operating Day

2

DA Economic NCPC Charge

Total Pool Day Ahead Economic NCPC Charges.  These charges are a result of NCPC Credits paid to Generators only.

3

DA Load Obligation

Total Pool Day Ahead Load Obligation used to allocate DA Economic NCPC Charges

4

DA Economic NCPC Rate

DA Economic NCPC Charge divided by DA Load Obligation

5

 

RT Economic NCPC Charge

Total Pool Real Time Economic NCPC Charges, These charges are a result of NCPC Credits paid to Generators and transactions at External Nodes.

6

RT NCPC Deviations

Total Pool Real Time NCPC Deviations used to allocate RT Economic NCPC Charges

7

RT Economic NCPC Rate

RT Economic NCPC Charge divided by RT NCPC Deviations

LSCPR NCPC tab

1

Operating Day

 

 

Operating Day

2

Region ID

Reliability Region Identification number.

3

Region Name

Reliability Region Name

4

DA LSCPR NCPC Charge

Total Pool Day Ahead LSCPR NCPC Charges

5

DA NCPC - Load Obligation Allocator

Total Day Ahead Pool Load Obligation per Reliability Region used to allocate DA LSCPR NCPC Charges.  As of 1/23/2014, Real Time Pool Load Obligation per Reliability Region will be used to allocate DA LSCPR Charges.

6

DA LSCPR NCPC Rate

DA LSCPR NCPC Charge divided by DA NCPC Load Obligation.  As of 1/23/2014, the rate will be the DA LSCPR NCPC Charge divided by RT NCPC Load Obligation.

7

RT LSCPR NCPC Charge

Total Pool Real Time LSCPR NCPC Charges

8

RT NCPC Deviations

Total Real Time Pool Real Time NCPC Deviations per Reliability Region used to allocate RT LSCPR NCPC Charge prior to March 1, 2005.

9

 

RT LSCPR NCPC Rate per MW Deviation

RT LSCPR NCPC Charges divided by RT NCPC Deviations

10

RT NCPC Load Obligation

Total Real Time Pool Load Obligation per Reliability Region used to allocate RT LSCPR NCPC Charge after March 1, 2005

11

RT LSCPR NCPC Rate per MW Load Obligation

RT LSCPR NCPC Charges divided by RT NCPC Load Obligation

External Node Economic NCPC tab

1

Operating Day

 

Operating Day

2

Trading Interval

Specific hour for which the information is reported. Numeric from 1 – 24 (For daylight-saving crossover days: the long day extra hour = 02X, the short day removes hour 02).

3

External Node Id

Numerical identifier for the External Node where the Day-Ahead transaction took place.

4

External Node Name

Name of the External Node where the Day-Ahead transaction took place.

5

 

NCPC Credit Type

Identifies the type of transaction(s) receiving the NCPC Credit.  If the NCPC Credits are for External Transaction purchases or Increment Offers then this column will be ‘IMPORT’. If the NCPC Credits are for External Transaction sales or Decrement Offers then this column will be ‘EXPORT’.

6

Day Ahead Economic NCPC Charge

Total Pool Day Ahead Economic NCPC Charges at the External Node for the hour.

7

Day Ahead Load Obligation per External Node

Total Pool Day Ahead Load Obligation used to allocate DA Economic NCPC Charges at the External Node for the hour. This column will be blank if the NCPC Credit Type is ‘EXPORT’.

8

Day Ahead Generation Obligation  per External Node

Total Pool Day Ahead Generation Obligation used to allocate DA Economic NCPC Charges at the External Node for the hour. This column will be blank if the NCPC Credit Type is ‘IMPORT’.

9

Day Ahead Economic NCPC Rate

Day Ahead Economic NCPC Charge per MW at the External Node for the hour.

VAR NCPC (Exclude High Voltage)

1

Operating Day

Operating Day

2

Trading Interval

Specific hour for which the information is reported. Numeric from 1 – 24 (For daylight-saving crossover days: the long day extra hour = 02X, the short day removes hour 02).

3

Monthly Regional Network Load and Hourly Reserved Capacity

Total Pool Monthly Regional Network Load and Pool Hourly Reserved Capacity 

4

Day Ahead VAR NCPC Charge

Total Pool Day Ahead VAR Service NCPC Charges. These charges are a result of Day Ahead NCPC VAR Credits paid for Cost of Energy Produced not related to high voltage conditions.

5

Day Ahead VAR NCPC Charge Rate

Day Ahead VAR NCPC Charge divided by Monthly Regional Network Load and Hourly Reserved Capacity.

6

Real Time VAR NCPC Charge

Total Pool Real Time VAR Service NCPC Charges.  These charges are a result of Real Time NCPC VAR Credits paid for Cost of Energy Produced, Cost of Energy Consumed, and Lost Opportunity Cost for VAR service not related to high voltage conditions. This also includes any High Voltage VAR Cost Reallocation credits done through a standard settlement.

7

Real Time VAR NCPC Charge Rate

Real Time VAR NCPC Charge divided by Monthly Regional Network Load and Hourly Reserved Capacity.

High Voltage VAR NCPC

1

Operating Day

Operating Day

2

Trading Interval

Specific hour for which the information is reported. Numeric from 1 – 24 (For daylight-saving crossover days: the long day extra hour = 02X, the short day removes hour 02).

3

Reliability Region ID

Reliability Region Identification number

4

Reliability Region Name

Reliability Region Name

5

Monthly Regional Network Load for Reliability Region

Total Regional Network Load value for the Reliability Region

6

Day Ahead High Voltage VAR NCPC Charge

Total Day Ahead VAR Service NCPC Charges. These charges are a result of Day Ahead NCPC VAR Credits paid for Cost of Energy Produced for VAR Service related to high voltage conditions.

7

Day Ahead High Voltage VAR NCPC Charge Rate

Day Ahead VAR High Voltage NCPC Charges divided by Monthly Regional Network Load for the Reliability Region.

8

Real Time High Voltage VAR NCPC Charge

Total Real Time VAR Service NCPC Charges.  These charges are a result of Real Time NCPC VAR Credits paid for Cost of Energy Produced, Cost of Energy Consumed, and Lost Opportunity Cost for VAR Service related to high voltage conditions. This also includes any High Voltage VAR Cost Reallocation charges done through a standard settlement.

9

Real Time High Voltage VAR NCPC Charge Rate

Real Time High Voltage VAR NCPC Charge divided by Monthly Regional Network Load for the Reliability Region.

Generator Performance Audit NCPC

1

Operating Day

Operating Day

2

Generator Performance Audit NCPC Charge

Pool total Generator Performance Audit NCPC Charges.

3

Generator Performance Audit Charge RTLO

Pool total Generator Performance Audit Real Time Load Obligation, used to allocate Generator Performance Audit NCPC Charges.

4

Generator Performance Audit NCPC Charge Rate

Generator Performance Audit NCPC Charge divided by Generator Performance Audit Charge RTLO.

 

Archive Status

Report Name

Change Summary

Effective Date

ww_ncpcsum Modified. New section "Generator Performance Audit NCPC" will appear with the initial NCPC settlement of September 2013 (report released in October). 09.01.2013
ww_ncpcsum Modified. New sections "VAR NCPC (Exclude High Voltage)" and "High Voltage VAR NCPC" will appear with the initial NCPC settlement of February 2013 (report released in March). These two new VAR sections will have the initial settlement data for the month prior to the settlement month. All resettlement reports will contain settlement data for the specified settlement month in all sections. Reports for the months of June 2012 through October 2012 will be regenerated shortly after 3/12/2013. 02.01.2013
ww_ncpcsum Modified. The Report Description has been changed. 06.01.2010