On January 2, 2024, the Federal Energy Regulatory Commission (FERC) approved a one-year delay to Forward Capacity Auction (FCA) 19 associated with the 2028-2029 Capacity Commitment Period (CCP). Pursuant to Tariff revisions that FERC accepted as part of the filing that effected the FCA 19 delay, the ISO will conduct an interim reconfiguration auction (RA) qualification process in 2024 to support RA participation for resources that have never obtained a Capacity Supply Obligation (CSO).
The ISO has added a new interim RA qualification section<https://www.iso-ne.com/markets-operations/markets/forward-capacity-market/fcm-participation-guide/interim-reconfiguration-auction-qualification> to the Forward Capacity Market Participation Guide, which contains materials related to interim RA qualification process participation.
Contact Participant Support and Solutions at (413) 540-4220 or askiso@iso-ne.com<mailto:askiso@iso-ne.com> or via an AskISO Case with any questions.