Produced daily, the Morning Report provides the ISO's best estimate of expected capacity available to meet peak-hour electricity demand and reserve requirements - key parameters used to operate the power system reliably.
For the weekly forecast, see the Seven-Day Capacity Forecast.
View the Morning Report below or Download a CSV file. Hover over items for an explanation.
Operational Capacity Update Report
Today's Information
3. Operable Capacity Analysis |
(MW) |
A. Capacity Supply Obligation (CSO)
|
26,074 |
B. Capacity Additions EcoMax Bid > CSO
|
822 |
C. Generation Outages and Reductions (Planned + Forced)
|
1,485 |
|
Planned Outages and Reductions
|
300 |
|
|
Forced Outages and Reductions
|
1,185 |
|
D. Uncommitted Available Generation (non-fast-start)
|
3,345 |
|
Uncommitted Available Non-Fast Before Peak (Info only)
|
875 |
|
E. DRR Capacity
|
223 |
F. Uncommitted Available DRR
|
12 |
G. Capacity Deliveries: Net Purchases = (-) Net Sales = (+)
|
|
|
Highgate |
-225 |
|
|
NB |
-327 |
|
|
NECEC |
0 |
|
|
NYISO AC |
-350 |
|
|
NYISO CSC |
330 |
|
|
NYISO NNC |
-30 |
|
|
Phase 2 |
-1,601 |
|
|
Net Deliveries
|
|
-2,203 |
H. Total Available Capacity (A+B-C-D+E-F-G)
|
24,480 |
I. Peak Load Forecast For Hour Ending 19
|
19,550 |
J. Total Operating Reserve Requirement
|
2,545 |
K. Capacity Required = I+J
|
22,095 |
L. Surplus = (+) Deficiency = (-) (H - K)
|
2,385 |
M. Replacement Reserve Requirement
|
160 |
N. Excess Commitment Surplus = (+) Deficiency = (-) (L - M)
|
2,225 |
4. Largest First Contingency |
(MW) |
____ |
1,601 |
8. Weather Forecast Summary for the Peak Hour
|
CITY |
CONDITIONS |
WIND |
HIGH TEMP (°F) |
Boston
|
Cloudy |
E-10 |
72 |
Hartford
|
Thunderstorms |
E-6 |
84 |
9. Units Committed to Meet Minimum Operating Reserve and Replacement Reserve Requirements
|
(MW) |
0 Units
|
0 |
Report Generated 07/09/2025 12:00 EDT
Download a CSV file of this Morning Report
.