After completing the interconnection study process, you must submit final data and register your asset.
On this page:
You must meet the following deadlines for submitting data into the Dynamics Data Management System (DDMS):
Note that if your facility data differ from what was studied in the System Impact Study, your project may be subject to a Material Modification Determination (MMD) Analysis. See Submitting Revised Data for more information.
See the Generator, Asset-Related Demand, and Alternative Technology Regulation Resource Asset Registration page for instructions on how to register your asset.
Contact the ISO’s New Generation Coordinator team, at NewGenCoord@iso-ne.com about metering, applicable data communication circuits and related equipment, system integration, asset registration, power system model updates, and other issues at least one year before the synchronization date.
Previous step: Execute an Interconnection Agreement